Owner · Architect · Contractor

OAC Meeting Minutes Template

A specialized meeting minutes template designed specifically for weekly or bi-weekly Owner-Architect-Contractor progress meetings. Formatted to establish clear Ball-in-Court accountability and protect project schedule baselines.

TEMPLATE // OAC_MEETING_MINUTES.TXT
OWNER-ARCHITECT-CONTRACTOR (OAC) MEETING MINUTES
Executive Progress Record · Objection Window: 48 Business Hours
Project Name [Project Name]
Job / Contract # [Contract Number]
OAC Meeting Number OAC #[00]
Date & Time [Date, 00:00 AM/PM]
Meeting Chair (GC PM) [GC Project Manager Name]
Meeting Location Field Office / Conference Call
1.00 EXECUTIVE ATTENDEE ROSTER
Role Representative Organization Attendance
Owner Representative[Owner Rep Name][Owner Entity]Present
Architect of Record[Principal Architect][Architecture Firm]Present
Structural Engineer[Engineer Name][Engineering Firm]Present
GC Project Manager[PM Name][General Contractor]Present
GC Superintendent[Super Name][General Contractor]Present
2.00 OWNER DIRECTIVES & DECISIONS
2.01 Lobby Finishes Authorization: Owner Rep confirmed approval of Terrazzo Sample #2 (Warm Matte Gray). Directs GC to procure materials. Confirmed no impact to contract baseline duration. BIC: GC (Procurement).
2.02 Tenant Fit-Out Scope Addition: Owner requested pricing for 4th-floor acoustic ceiling tile upgrade. GC to prepare preliminary cost proposal within 10 business days. BIC: GC Estimating.
3.00 OPEN RFIs AFFECTING CRITICAL PATH
3.01 RFI 104 — Level 4 Structural Opening: Architect response confirmed issued Sept 12 approving 42" penetration. Framing crew cleared to proceed without delay claim. Status: Closed.
3.02 RFI 108 — Roof Anchor Tieback Detail: Structural engineer reviewing safety load calculations. Turnaround required by Friday to avoid waterproofing milestone delay. BIC: Structural Engineer.
4.00 CRITICAL SUBMITTALS & LONG-LEAD PROCUREMENT
4.01 Submittal 082 — Switchgear Cut Sheets: Electrical subcontractor submittal in consultant review. Review deadline: Sept 20. Factory lead time confirmed at 26 weeks. BIC: Electrical Engineer.
4.02 Elevator Cab Finishes: Elevator manufacturer awaiting final owner color selection. Delay beyond Sept 25 will push hoistway turnover. BIC: Owner Rep.
5.00 PROJECT SCHEDULE & MILESTONES
5.01 Dry-In Milestone: Building envelope dry-in tracking on target for November 15. Curtainwall installation on south elevation commences next Monday.
5.02 Permits & Inspections: Fire department hydro test for standpipe system approved on September 10. Underground utility sign-off pending city inspector visit Thursday.
6.00 POTENTIAL CHANGE ORDERS (PCOs) & ALLOWANCE LOG
6.01 PCO 039 — Unforeseen Foundation Obstruction: Subsurface concrete mass encountered during elevator pit excavation. Formal ticket reconciliation submitted for $14,200. Under owner review. BIC: Owner Rep.
6.02 Allowance #3 — Landscaping Package: Preliminary pricing received from landscape sub. Current buyout reflects $8,500 under allowance budget. Credit to be reconciled in next billing cycle.
7.00 OAC ACTION ITEM REGISTER
Item # Action Required Ball-in-Court (BIC) Committed Due Date Status
OAC-14.1 Return response on RFI 108 (Roof tieback detail) Structural Engineer Sept 18 Open
OAC-14.2 Finalize elevator cab interior finish selection Owner Rep Sept 22 Open
OAC-14.3 Submit revised PCO 039 documentation GC Project Manager Sept 19 In Review
NEXT MEETING SCHEDULE
The next OAC meeting (OAC #[00+1]) is scheduled for [Next Date] at [Time] in the Jobsite Trailer. Please submit any additions or corrections within 48 hours.