PRECONSTRUCTION COORDINATION MEETING MINUTES
Official Preconstruction Record · Document Ref: PRECON-MIN-[00]
1.00 DESIGN COORDINATION & DRAWING MILESTONES
1.01
Drawing Issuance: Architect confirmed 100% Construction Document package will be issued for final trade pricing on [Date]. MEP design-assist narratives incorporated into general specifications.
1.02
Building Department Plan Check: Initial plan check comments received from City Building Dept. Structural engineer submitting response sketches for foundation calculations by [Target Date]. BIC: Structural Engineer.
2.00 VALUE ENGINEERING (VE) DECISION LOG
| VE Item # | System / Scope Description | Estimated Credit | Status | Approved By |
|---|---|---|---|---|
| VE-014 | Substitute magnetic-bearing centrifugal chiller for standard chiller | $84,000 | Approved | Owner Rep ([Date]) |
| VE-022 | Alternative roofing membrane with equivalent 20-yr warranty | $42,500 | In Review | Architect Review |
| VE-031 | Revise exterior storefront mullion profile from custom to standard | $28,000 | Rejected | Aesthetic Grounds |
3.00 BID PACKAGES & SCOPE INTERFACE BOUNDARIES
3.01
BP-03 Concrete / BP-05 Structural Steel Interface: Confirmed that anchor bolt setting will be performed by concrete subcontractor with templates supplied by steel fabricator.
3.02
BP-22 Plumbing / BP-23 HVAC Interface: Condensate drainage piping from fan coil units to indirect waste receptors allocated to Plumbing package. Mechanical scope ends at equipment connection.
4.00 ALLOWANCES & CONTINGENCIES
4.01
Site Utility Rock Excavation Allowance: Geotechnical report indicates potential shallow bedrock on west elevation. Recommended allowance established at $75,000 based on 500 CY unit rate.
4.02
Architectural Millwork Allowance: Current design selections exceed baseline allowance by $18,000. Architect presenting alternative veneer species at next coordination meeting. BIC: Architect.
5.00 LONG-LEAD PROCUREMENT REGISTER
5.01
Primary Electrical Switchgear: Current manufacturer lead time is 28 weeks from approved shop drawings. Owner authorized early procurement package release prior to GMP execution. BIC: GC Electrical Estimator.
6.00 ACTION ITEMS & DELIVERABLES
| Item # | Deliverable | Responsible Party | Due Date | Status |
|---|---|---|---|---|
| PRE-01 | Issue revised finish schedule for 100% CD pricing | Architect | Oct 05 | Open |
| PRE-02 | Execute early procurement agreement for switchgear | Owner Rep | Oct 08 | Open |
| PRE-03 | Finalize trade buyout scopes for BP-03 and BP-05 | Chief Estimator | Oct 12 | In Progress |
Bridge preconstruction context directly into field execution.
MinuteMate captures your preconstruction discussions and hands off the complete history to your Project Managers when the job breaks ground.