Preconstruction Meeting Minutes Template

Document design decisions, value engineering approvals, scope boundary agreements, and allowance allocations with complete contractual traceability prior to project buyout.

TEMPLATE // PRECONSTRUCTION_MEETING_MINUTES.TXT
PRECONSTRUCTION COORDINATION MEETING MINUTES
Official Preconstruction Record · Document Ref: PRECON-MIN-[00]
Project Name [Project Name]
Meeting Series Precon Review #[00]
Date & Time [Date, 00:00 AM/PM]
Current Milestone 100% DD Pricing / GMP Finalization
Recorded By [Precon Manager / Estimator Name]
1.00 DESIGN COORDINATION & DRAWING MILESTONES
1.01 Drawing Issuance: Architect confirmed 100% Construction Document package will be issued for final trade pricing on [Date]. MEP design-assist narratives incorporated into general specifications.
1.02 Building Department Plan Check: Initial plan check comments received from City Building Dept. Structural engineer submitting response sketches for foundation calculations by [Target Date]. BIC: Structural Engineer.
2.00 VALUE ENGINEERING (VE) DECISION LOG
VE Item # System / Scope Description Estimated Credit Status Approved By
VE-014 Substitute magnetic-bearing centrifugal chiller for standard chiller $84,000 Approved Owner Rep ([Date])
VE-022 Alternative roofing membrane with equivalent 20-yr warranty $42,500 In Review Architect Review
VE-031 Revise exterior storefront mullion profile from custom to standard $28,000 Rejected Aesthetic Grounds
3.00 BID PACKAGES & SCOPE INTERFACE BOUNDARIES
3.01 BP-03 Concrete / BP-05 Structural Steel Interface: Confirmed that anchor bolt setting will be performed by concrete subcontractor with templates supplied by steel fabricator.
3.02 BP-22 Plumbing / BP-23 HVAC Interface: Condensate drainage piping from fan coil units to indirect waste receptors allocated to Plumbing package. Mechanical scope ends at equipment connection.
4.00 ALLOWANCES & CONTINGENCIES
4.01 Site Utility Rock Excavation Allowance: Geotechnical report indicates potential shallow bedrock on west elevation. Recommended allowance established at $75,000 based on 500 CY unit rate.
4.02 Architectural Millwork Allowance: Current design selections exceed baseline allowance by $18,000. Architect presenting alternative veneer species at next coordination meeting. BIC: Architect.
5.00 LONG-LEAD PROCUREMENT REGISTER
5.01 Primary Electrical Switchgear: Current manufacturer lead time is 28 weeks from approved shop drawings. Owner authorized early procurement package release prior to GMP execution. BIC: GC Electrical Estimator.
6.00 ACTION ITEMS & DELIVERABLES
Item # Deliverable Responsible Party Due Date Status
PRE-01 Issue revised finish schedule for 100% CD pricing Architect Oct 05 Open
PRE-02 Execute early procurement agreement for switchgear Owner Rep Oct 08 Open
PRE-03 Finalize trade buyout scopes for BP-03 and BP-05 Chief Estimator Oct 12 In Progress

Bridge preconstruction context directly into field execution.

MinuteMate captures your preconstruction discussions and hands off the complete history to your Project Managers when the job breaks ground.